CCEA approved 4721 crore rupees road projects in Madhya Pradesh, Telangana
12:28
Posted by Test Blog
Who: 4721 crore rupees road projects
Where: Madhya Pradesh, Telangana
What: Approved by CCEA
When: 10 June 2015
Where: Madhya Pradesh, Telangana
What: Approved by CCEA
When: 10 June 2015
Highlights of the Madhya Pradesh Road Project
• The road project of Madhya Pradesh includes development of the four laning of the Guna-Biaora and Biaora-Dewas section of National Highway-3 in with an estimated cost of 2815.69 crore rupees.
• This will be done under the National Highways Development Project (NHDP) Phase-IV in Design, Build, Finance, Operate and Transfer (DBFOT) basis in BOT (Toll) mode.
• The cost for Guna-Biaora laning is estimated to be 1081.9 crore rupees including land acquisition, resettlement and rehabilitation and other pre-construction activities. The total length of the road will be approximately 93.5 kms.
• The total cost for Biaora-Dewa section will be about 1733.79 crore rupees including cost of land acquisition, resettlement and rehabilitation and other pre-construction activities. The total length of the road will be approximately 141.26 kms.
Highlights of the Telangana Road Project
• The road project of Telangana includes development of the four laning of the Yadgiri-Warangal section of National Highway- 163. This work will be under the NHDP Phase-IV.
• The approval was given on Engineering, Procurement and Construction (EPC) basis.
• The cost of the project is estimated to be 1905.23 crore rupees including cost of land acquisition, resettlement and rehabilitation and other pre-construction activities. The total length of the road will be approximately 99 kms.
• After completion of the project, the whole stretch from Hyderabad to Warangal would be 4-laned.
• The road project of Madhya Pradesh includes development of the four laning of the Guna-Biaora and Biaora-Dewas section of National Highway-3 in with an estimated cost of 2815.69 crore rupees.
• This will be done under the National Highways Development Project (NHDP) Phase-IV in Design, Build, Finance, Operate and Transfer (DBFOT) basis in BOT (Toll) mode.
• The cost for Guna-Biaora laning is estimated to be 1081.9 crore rupees including land acquisition, resettlement and rehabilitation and other pre-construction activities. The total length of the road will be approximately 93.5 kms.
• The total cost for Biaora-Dewa section will be about 1733.79 crore rupees including cost of land acquisition, resettlement and rehabilitation and other pre-construction activities. The total length of the road will be approximately 141.26 kms.
Highlights of the Telangana Road Project
• The road project of Telangana includes development of the four laning of the Yadgiri-Warangal section of National Highway- 163. This work will be under the NHDP Phase-IV.
• The approval was given on Engineering, Procurement and Construction (EPC) basis.
• The cost of the project is estimated to be 1905.23 crore rupees including cost of land acquisition, resettlement and rehabilitation and other pre-construction activities. The total length of the road will be approximately 99 kms.
• After completion of the project, the whole stretch from Hyderabad to Warangal would be 4-laned.
This entry was posted under Current-AffairsJobPatrika=>
Current Affairs 2015,
June
. Follow any responses to this post through RSS. You can leave a response, or trackback from your own site.
Subscribe to:
Post Comments (Atom)